Following multiple postponements of the mission that will send four astronauts on a journey around the moon, NASA conducted a press briefing today, revealing that Artemis II is set to potentially launch as soon as April 1.
“At the conclusion of the FRR, all teams have expressed their readiness to proceed with the launch and flight of Artemis II around the moon, contingent upon the completion of certain tasks,” stated Lori Glaze, the acting associate administrator for the Exploration Systems Development Mission Directorate.
“Just a reminder for everyone. We mention this every time we discuss this flight. This is a test flight. It carries inherent risks. However, our team and equipment are prepared. We plan to roll out to the launch pad next week,” she added.
The press conference today focused on NASA’s flight readiness review, a critical final step before the launch.
Glaze also mentioned that an additional date has been included in the launch window: April 2. This indicates that the Artemis II mission can take off anytime between April 1 and April 6.
The Artemis II mission will feature Canadian Space Agency astronaut Jeremy Hansen, along with NASA astronauts Reid Wiseman, Victor Glover, and Christina Koch, as they embark on a flight path around the moon.

An official crew portrait for Artemis II, from left: NASA Astronauts Christina Koch, Victor Glover, Reid Wiseman, and Canadian Space Agency Astronaut Jeremy Hansen. Taken in March 2023. (NASA)
The astronauts will enter quarantine starting March 18 and will travel to the Kennedy Space Center on March 27.
NASA’s Space Launch System (SLS) was transported to the launch pad in January with an intended launch in February. However, the rocket first needed to complete a wet dress rehearsal, which involves a simulation of the launch process, including fueling with hydrogen and liquid oxygen.
What caused the delays?
During the initial wet dress rehearsal, the rocket encountered hydrogen leaks, a complication that was also seen during the uncrewed Artemis I wet dress rehearsal. This led to the next launch window being pushed to early March.
NASA carried out a second wet dress rehearsal on February 19. Although it seemed to resolve the hydrogen leak issue, a subsequent problem with helium flow to the upper-stage engines was detected. Consequently, the rocket was returned to the Vehicle Assembly Building (VAB) on February 25, and NASA ruled out a March launch.
-
NASA’s moon rocket experiences fuel leak during critical test ahead of launch
-
NASA delays Artemis II launch due to hydrogen leak during rehearsal
NASA has since resolved the helium issue, replaced batteries for the SLS upper stage, core stage (the orange tank), and solid rocket boosters, and is set to retest the flight termination system, which would obliterate the rocket in case of a loss of control.
Last month, newly appointed NASA administrator Jared Isaacman announced a modification to the Artemis program, indicating that Artemis III will no longer aim for a lunar landing. Instead, it will serve as a test mission to dock with one of its lunar landers, developed under contracts with SpaceX and Blue Origin.